Metropolitan Transportation Network SOC Project

  • Future of Yeongcheon
  • Yeongcheon-si 10 Strategic Projects
  • Metropolitan Transportation Network SOC Project

Building Private Financed Highway between Yeongcheon ~ Sangju

Project Summary
  • Location : Impo-ri, Bukan-myeon, Yeongcheon-si ~ Seunggok-ri, Nakdong-myeon, Sangju-si
  • Extension : L=93.95km(4-lane), Yeongcheon-si section L=36.30km
  • Project Period : 2011~2016(6 years)
  • Project Cost : 1,132,500 mil. KRW (Private)
  • Facility : Interchange 4 spots, Junction 4 spots, Rest Area 2 spots
  • Enforcement Office : Yeongcheon-Sangju Highway Inc.
Progress
  • Apr. 18, 2003: Submitted initial proposal to the Ministry of Construction and Transportation
  • Dec. 31, 2008: Concluded enforcement agreement and appointed project operator
  • Mar. 10, 2009: Finished traffic impact assessment deliberation
  • Oct. 27, 2009: Finished preliminary disaster effect review consultation
  • Dec. 30, 2010: Applied for enforcement design approval to the Ministry of Land, Transport and Maritime Affairs
  • Feb. 2012: Enforcement design approved by the Ministry of Land, Transport and Maritime Affairs
  • Apr. 2012: Began construction
Future Plan
  • Apr. 2017: Completed construction

National Highway No. 35(Yeongcheon~Samchang) extension

Project Summary
  • Location : Omi crossroad, Yeongcheon-si ~ Geumho-ri, Hwanam-myeon
  • Project Cost : 43,600 mil. KRW (Governmental)
  • Entire extension : L=6.78km
    • Omi crossroad ~ Bukyeongcheon IC Section : L=4.30km (2→4-lane)
    • Samchang Detour Road : L=2.48km (2-lane created)
  • Project Period : 2011~2017 (7 years)
  • Enforcement office: Busan Regional Construction and Management Administration
Progress
  • Nov. 29, 2007. Performed feasibility study and basic design service
  • Nov. 28, 2009. Finished basic design
  • Dec. 19, 2011. Initiated enforcement design service
  • Dec. 12, 2012. Finished enforcement design service
Expected Effect
  • Solves traffic congestion, reduces logistics cost, and promotes balanced development to activate local economy
  • Improves linear faulty and narrow section of lane width to reduce traffic accident rate
National-Support-Local Road No. 69(Jogyo ~ Imgo) extension
Project Summary
  • Location : Jogyo-dong, Yeongcheon-si ~ Yanghang-ri, Imgo-myeon
  • Project Cost : 35,600 mil. KRW(Governmental)
  • Extension : L=5.32km, B=19.50m
  • Project Period : 2012~2016(5 years)
  • Enforcement office : Busan Regional Construction and Management Administration
Progress
  • Nov. 2007. ~ Dec. 2009. Finished enforcement design service (Busan Regional Construction and Management Administration)
  • Apr. 26, 2011. Accepted design drawings (Busan Regional Construction and Management Administration → Gyeongbuk-do)
Problems
  • Ministry of Land, Transport and Maritime Affairs notified to amend the 2nd National Highway•National-Support-Local Road construction 5-year plan (4-lane→2-lane)
    ※ Ministry of Land, Transport and Maritime Affairs, Department of Arterial Road-3503(Dec. 15, 2011.)
  • Supplementary design service for the enforcement design service between Jogyo~Imgo (Jun. 2012 ~ Jun. 2013)
  • Mass civil appeals for the change of project from 4-lane design project into 2-lane
Future Plan
  • Propose 4-lane enforcement to resolve the distrust in government policy and mass civil appeals by considering the opening of private financed highway between Yeongcheon ~ Sangju and increased traffic due to surrounding area development