  • Future of Yeongcheon
  • Yeongcheon-si 10 Strategic Projects
  • City Road Network Expansion

Road construction between Changsin Apartment~Omi-dong

Project Summary
  • Project Period : 2012~2015(4 years)
  • Project Cost : 9,800 mil. KRW
  • Project Section : Jeongyeongdae Changsin APT ~ Omi village
  • Major Facilities : Road construction L=1.5km, B=20m
Progress
  • Sep. 2012. Finished enforcement design
Reinforcing Method
  • Among 9.8 billion KRW of Total Project Cost, 600 mil. KRW was executed in 2012 and 800 mil. KRW is secured for 2013; however, it is necessary to secure additional budget for smooth progress of project and early completion of the project.

Road expansion and pavement between Munnae Jugong APT and Omi three-way intersection

Project Summary
  • Project Period : 2009~2015(7 years)
  • Project Cost : 23.5 billion KRW
  • Project Section : Munnae Jugong APT ~ Omi three-way intersection
  • Major Facilities : Road expansion and pavement L=1.6km, B=24m
Progress
  • Apr. 2009. Enforcement design service
  • 2010. Consultation for compensation
Reinforcing Method
  • Among 23.5 billion KRW of Total Project Cost, 5.5 billion KRW has been executed and 3 billion KRW budget is secured for 2013; however, it is necessary to secure additional budget for smooth progress of project and early completion of the project.
Road expansion and pavement between Munnae Jugong APT and Omi three-way intersection