Successful Construction of Yeongcheon Horse Race Park
- Future of Yeongcheon
- Yeongcheon-si 10 Strategic Projects
- Successful Construction of Yeongcheon Horse Race Park
Yeongcheon Horse Race Park
Project Summary
- Location: Seongcheon/Daemi-ri, Geumho-eup and Daepyeong-ri, Cheongtong-myeon, of Yeongcheon-si area
- Area : 1,480,000㎡
- Major Facilities : horse racing facility, racehorse training and citizen's park facility, etc.
In a mobile environment, you can move left and right to view the content (table).
Yeongcheon Horse Race Park - Horse implementation facility, Racehorse training facility, Park facility Horse implementation facility Racehorse training facility Park facility Stand: 20,000 seats
Track: 3 planesStables: 1,100 rooms
Training facility: round race course, practice race courseCitizen's park
Riding facility - Project Cost : 365.7 billion KRW
- Project Period : 2012~2016(5 years)
Progress
- Dec. 2009. Yeongcheon is determined as proposed stie for the 4th Horse Race Park Location
- Feb. 2010. Established business agreement (Gyeongbuk-do·KRA·Yeongcheon-si)
- Jul. 2010. Applied to KRA business license (Ministry for Food, Agriculture, Forestry and Fisheries)
- Sep. 2012. Provincial Assembly adopted ‘Speedy Progress of Yeongcheon Horse Race Park and Provincial Tax Exemption’
- Sep. 2012. Ministry for Food, Agriculture, Forestry and Fisheries permitted Yeongcheon Horse Race Park construction business
Korea Racing Authority website : http://www.kra.co.kr
Future Plan
- Jan. 2013. Determine project site boundary; investigated land for sale
- Jun. 2014. Finish compensation for transferred site; approved enforcement plan and began construction of Yeongcheon Horse Race Park
- Oct. 2015. Secure KRA jockey, manager and other manpower
- Dec. 2016. Complete Yeongcheon Horse Race Park
Extending and paving roads around Yeongcheon Horse Race Park
Project Summary
- Location : Cheongtong-myeon, Geumho-eup, Yeongcheon-si area
- Project Period : 2013~2016(4 years)
- Total Project Cost : 63,000 mil. KRW
- Project capacity
- Daepyeong-ri~Cheongtongwa-chon IC : L=4.50km, B=20.0m (33 billion KRW)
- Institute of Cultural Property~Seongcheon-ri, Geumho-eup: L=2.90km, B=20.0m (19 billion KRW)
- Police Station Crossroad~Seokseom-ri, Geumho-eup: L=1.80km, B=20.0m (11 billion KRW)
Progress
- May 27, 2010. Enforcement Design Service ordered
- Jul. 22, 2010. Enforcement Design Service began (Dec. 10, 2010 Service stop)
Future Plan
- Dec. 2012. Finish Enforcement Design Service
- Jan. 2013. Begin compensation for road site
- 2014.~2016. Construction beginning~completion